Sample PMP® Question: April 2016


Question

When any request forces changes to the plan, an experienced project manager only implements the changes after receiving an approved change request, to maintain the integrity of baselines. This is done as a part of:

  1. Monitor and Control Project Work.
  2. Develop Project Management Plan.
  3. Direct and Manage Project Work.
  4. Perform Integrated Change Control.

 

Answer

A.  The Integrated Change Control process maintains the integrity of baselines, and takes place from the beginning of the project to its end.

 

Based on question data supplied by: 1000 Challenge PMP Questions
Author: Mohit Arora
Available now at amazon.com

Leave a comment

Your email address will not be published. Required fields are marked *