Sample PMP Question: January 2015 2 comments


While selecting projects, the sponsor directs you as the project manager to pick the BEST project your company can pursue.  Considering the following options, which project would you recommend:

A.    Project A with a BCR of 3:1
B.    Project B with a BCR of 2:1
C.    Project C with a BCR of 5:2
D.    Project D with a BCR of 5:4

Answer

A: You should pick the project with the highest Benefit Cost Ratio (BCR).  A is therefore the best option.

Question data supplied by: 1000 Challenge PMP Questions
Author: Mohit Arora
Available now at amazon.com


Leave a comment

Your email address will not be published. Required fields are marked *

2 thoughts on “Sample PMP Question: January 2015