What are Project Exclusions?


What would be an example of a project exclusions in a project initiation document in project management? When I look it up I’m told things that are not covered in the project? Surely that could mean anything?

project exclusions

Yes, it could be anything, but it’s all about managing stakeholder expectations. What might people think is part of the project, but really it isn’t? If you’re building a house, perhaps the interior decorating is defined as outside the scope of your project, or perhaps the landscaping is out-of-scope. Exclusions are often mentioned in project charter documents and/or project scope statements, and are sometimes referred to as project boundaries.

In the Project Management Institute’s sixth edition PMBOK Guide, project exclusions are documented as part of the Project Scope Statement, along with the product scope description, deliverables, and acceptance criteria. (Refer to pages 154 and 155.)

Read more about the basic project management process. You can also read more about project definition as part of our Ten Ds of project management series.

Key Consulting provides live online and in-person project management consulting, project management best practice, and Microsoft Project training courses, using Project Management Institute (PMI) best practices and standards.  If you need help with anything related to project management feel free to contact us.


About Kevin Archbold

Kevin Archbold, PMP, PMI-SP, has over 30 years of project management experience with large and small organizations in a variety of industries, including automotive, nuclear, telecommunications, trucking, IT, recruiting, mining, construction, and government. Kevin has presented at local and national levels within the Project Management Institute (PMI), is the winner of a local chapter PMI Project of the Year Award, and is the current president of a PMI Chapter.