You are developing a statement of work for the procurement of some raw materials for your project.  What should you focus on in developing the statement of work?

  1. The charter and the scope statement, to ensure the project is understood.
  2. The project requirements, detailing them sufficiently for the vendors to make suitable proposals.
  3. Detailed attributes of the requested deliverables, to allow vendors to submit suitable bids.
  4. The Work Breakdown Structure, which should be broken down to the work package level and the WBS dictionary.

 

Answer

C: A statement of work focuses on the product and its specifications, as expected to be delivered by the subcontractor.

 

Question data supplied by: 1000 Challenge PMP Questions
Author: Mohit Arora
Available now at amazon.com


About Kevin Archbold

Kevin Archbold, PMP, PMI-SP, has over 30 years of project management experience with large and small organizations in a variety of industries, including automotive, nuclear, telecommunications, trucking, IT, recruiting, mining, construction, and government. Kevin has presented at local and national levels within the Project Management Institute (PMI), is the winner of a local chapter PMI Project of the Year Award, and is the current president of a PMI Chapter.

Leave a comment

Your email address will not be published. Required fields are marked *