Sample PMP Question: January 2014 1 comment


You are responsible for a construction project currently under execution.  You’re closely evaluating the work by constantly measuring the project performance, and recommending changes, repairs, and correction action where necessary.  What process are you performing?

A.     Perform Quality Assurance
B.     Integrated Change Control
C.     Control Scope
D.     Monitor and Control Project Work

Answer

D: Monitoring and controlling means measuring the performance of the project against the project management plan, and approving change requests, taking corrective or preventive actions to keep the project on track to deliver the expected results or product or service.

Question data supplied by: 1000 Challenge PMP Questions
Author: Mohit Arora
Available now at amazon.com


About Kevin Archbold

Kevin Archbold, PMP, PMI-SP, has over 30 years of project management experience with large and small organizations in a variety of industries, including automotive, nuclear, telecommunications, trucking, IT, recruiting, mining, construction, and government. Kevin has presented at local and national levels within the Project Management Institute (PMI), is the winner of a local chapter PMI Project of the Year Award, and is the current president of a PMI Chapter.

Leave a comment

Your email address will not be published. Required fields are marked *

One thought on “Sample PMP Question: January 2014

  • Kimberly Ferreira

    Hi,

    I have participated in 3 PMI exam development workshops. The questions on the exam are written by PMPs and have rigorous standards that are followed. It is fun to work with professionals across industry and challenging to ensure we are meeting the high expectations that are set.