A housing construction project requires that governmental environmental hearings be held prior to site preparation. From a project management prospective, this is an example of?
a. Risk Breakdown Structure
b. Critical Path Activity
c. External Dependency
d. Enterprise Environmental Factor
c. An external dependency involves a relationship between project and non-project activities.