During the project life-cycle, stakeholder identification is expected to be:
A. A continuous process.
B. One of the key responsibilities of the project manager and the project sponsor.
C. Dependent on the project charter.
D. Focused only on stakeholders who will be impacted as a result of the project.
Answer
A: Stakeholder identification will continue throughout the project life-cycle. As the project proceeds though each phase, additional stakeholders may become involved, while others will be released. Stakeholder identification is conducted primarily by the project management team, but some stakeholders may be identified in the project charter.
Question data supplied by: 1000 Challenge PMP Questions