While selecting projects, the sponsor directs you as the project manager to pick the BEST project your company can pursue. Considering the following options, which project would you recommend:
A. Project A with a BCR of 3:1
B. Project B with a BCR of 2:1
C. Project C with a BCR of 5:2
D. Project D with a BCR of 5:4
Answer
A: You should pick the project with the highest Benefit Cost Ratio (BCR). A is therefore the best option.