Sample PMP Question: January 2015 2 comments
While selecting projects, the sponsor directs you as the project manager to pick the BEST project your company can pursue. Considering the following options, which […]
While selecting projects, the sponsor directs you as the project manager to pick the BEST project your company can pursue. Considering the following options, which […]
I want to prepare to take the Project Management Certification and I want to pass on the first try. Anyone know of any good certification […]
During the project life-cycle, stakeholder identification is expected to be: A. A continuous process. B. One of the key responsibilities of the project […]
You are developing a statement of work for the procurement of some raw materials for your project. What should you focus on in developing the […]
How many lines of communication are there on your project, if your project involves 17 people excluding the sponsor: A. 112 B. 105 […]
John completed the risk analysis and he knows that the expected value is 100 days with a standard deviation of 12 days. John can be […]
You are the project manager on a software implementation project. Your client demands a major change in the later phase of the project. You assess […]
The theory of zero defects is based on: A. Prevention B. Inspection C. Correction D. Fitness for Use Answer A: This theory […]
The project manager is executing a railroad construction project, when his sponsor asks him to forecast the cost of project completion. Which of the following […]
Your project has four activities, which will require the following amounts of time: A=2 days, B=3 days, C=1 day, and D=5 days. B can start […]